Transformer trip interrupts supply at Sebokeng substation
July 2022Published 3 Oct 2026Responsible editor: Chief Editor
Get the next one by email
Free alerts on grid infrastructure incidents in South Africa, and an email when EIR-1950 is updated. No account needed; unsubscribe in one click.
Confirm your email and every substation and transformer incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
What happened
A transformer at the Sebokeng substation tripped around 21:00 on 26 July 2022 while repairs were under way following an earlier fire. Essential services and customers in Sebokeng lost supply. Restoration work continued with a target of 29 July 2022. Rotational supply was provided to some zones using temporary measures, but Golden Gardens remained without supply due to network configuration.
Contributing factors
The trip occurred during ongoing repairs and replacement of equipment damaged in the fire of 18 July 2022.
Lessons learned
- Maintain contingency supply arrangements for essential services during substation repairs.
- Assess network configuration constraints before relying on temporary feeds.
- Update restoration timelines promptly when damage scope exceeds initial estimates.
More lessons on outages, backup supply and restoration, from every incident on the register.
Source
Published 2026-10-03. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.