Rooftop solar panels catch fire at Apple's Mesa plant being converted to a data centre
May 2015Published 2 Oct 2026Updated 13 Oct 2026Responsible editor: Chief Editor
Get the next one by email
Free alerts on solar PV incidents in the United States, and an email when EIR-1886 is updated. No account needed; unsubscribe in one click.
Confirm your email and every solar incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): Apple
What happened
On 26 May 2015 a fire broke out on the roof of a 1.3 million square foot plant in Mesa, Arizona, which Apple had acquired from GT Advanced and was converting into a data centre. Apple bought the plant in 2013 to make sapphire glass, and announced in February 2015 that it would convert it. Local reports said the rooftop, fitted with hundreds of solar panels, was on fire, and that a second blaze had started inside the building.
Crews from Mesa, Gilbert and Superstition Fire and Medical District brought the fire under control in about 35 minutes. A section of the roof over a loading dock partly collapsed. Reports gave between 40 and 50 people evacuated, citing the Arizona Republic, while AP reported about 45 workers evacuated. No injuries were reported.
Contributing factors
A Mesa fire official said the blaze may have been sparked by the rooftop solar panels. ABC 15 reported that the fire appeared to have originated on the panels. No confirmed cause had been published, and authorities were investigating. The fire was confined to a section of roof over a loading dock. The building was mid-conversion and was not reported to be operating as a data centre.
Lessons learned
- Where a building is being converted or taken over, check that its rooftop PV arrays, DC cabling and combiner boxes are in working order before they are energised.
- Give fire crews plans showing where rooftop solar arrays are and how to isolate them before water is applied.
- When a building is being repurposed, check that its roof structure can carry the added load of PV and that fire spread over loading areas has been assessed.
More lessons on design, standards and commissioning, fire suppression and firefighting, spacing, layout and fire spread, from every incident on the register.
Source
Other entries that name Mesa
Published 2026-10-02. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.