Harvard substation explosion cuts power across Bloemfontein

Mar 2023Published 2 Oct 2026

Companies named in this entry: Centlec, Eskom

An explosion was reported at the Harvard Substation in Bloemfontein on the night of Monday 20 March 2023. The substation supplies electricity from Eskom to Centlec, the Mangaung Metro electricity supplier. Centlec said both 132 kV incomers had tripped on the supply to Mangaung and that this affected the entire city. The report described most of Bloemfontein as left in darkness. Hospitals were reported to be running on generators. Centlec said the restoration time could not be estimated until the fault was assessed, and the cause had not been identified at the time of reporting.

The cause of the explosion had not been identified when the report was published. Centlec said both 132 kV incomers had tripped.

  1. Loss of both incoming feeds at a city supply substation can black out a wide area, so operators should know how critical sites will be supplied if that happens.
  2. Public notices should say what is known and should not give a restoration time before the fault has been assessed.
  3. Hospitals and other essential sites need an alternative supply that can start without delay when the city feed is lost.

Other entries that name Bloemfontein

Published 2026-10-02. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.

Get the next one like this

One email when a newly reported incident is confirmed, at most two a day, plus a Monday digest. Free, no account needed, unsubscribe in one click.

By subscribing you agree to the privacy policy.

Related incidents

Grid infrastructure incidents in South Africa: 92 entries, with a free alert for the next one.

Browse the full register or submit an incident.