Transformer fire at Rutland substation cuts power to thousands
Apr 2005Published 14 Sept 2026Responsible editor: Chief Editor
- Where
- Lalor Avenue Substation in Rutland, Vermont
- What
- Transformer fire and explosion
- Injuries
- None reported
- Cause
- Under investigation
- Outcome
- Power cut to 3,000 customers for two and a half hours
Get the next one by email
Free alerts on grid infrastructure incidents in the United States, and an email when EIR-0710 is updated. No account needed; unsubscribe in one click.
Confirm your email and every substation and transformer incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): Central Vermont Public Service
What happened
A transformer fire and explosion occurred at the Lalor Avenue Substation in Rutland, Vermont, behind a General Electric plant, cutting power to about 3,000 Central Vermont Public Service customers for roughly two and a half hours on a Friday afternoon. Firefighters could not approach the flames for the first 20 minutes due to electrocution risk until power to the substation was shut down. One transformer was destroyed and a building housing equipment and a control centre was damaged.
No injuries were reported. The outage disabled traffic signals, requiring police to direct traffic, and forced two residents reliant on electrically powered oxygen tanks to be relocated to hospital until power was restored. The ruptured transformer also spilled a small amount of mineral oil containing low levels of PCBs, which required environmental cleanup.
Contributing factors
Utility officials said the cause was under investigation but believed a faulty switch or other equipment failure was responsible.
Lessons learned
- Transformer fire at a substation can delay firefighting for 20 minutes due to electrocution risk, so operators should rehearse rapid de-energisation with local fire services.
- A ruptured transformer can spill mineral oil containing PCBs, so sites should hold pre-planned spill response procedures and containment kits.
- Transformer failure can disable traffic signals and medical equipment, so contingency plans must identify and support vulnerable residents in the area.
More lessons on worker safety and safe systems of work, emergency response and public communication, from every incident on the register.
Not yet known
- Exact cause of the switch or equipment failure
- Transformer model and age
- Cost of damage and cleanup
- Duration of building repairs
This entry is updated when these are reported. Get an alert for the next one like it.
Source
Published 2026-09-14. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.