Planning pack for this site, £295Other options

Battery storage · United Kingdom

West Boldon Substation - Battery Energy Storage

Operator Whirlwind Energy Storage Limited

Awaiting Construction60 MWData checked 16 November 2026Source record dated 15 July 2025

Watch this siteIts outage notices and incidents, what it earns and where it ranks, in your workspace and by email. 7 days free, no card.

West Boldon Substation - Battery Energy Storage is a 60 MW battery storage site in The Boldons, Tyne And Wear, United Kingdom. Its planning application (ST/0486/23/FUL) went to South Tyneside on 17 July 2023 and was granted on appeal on 10 December 2024. Its status in the Renewable Energy Planning Database (UK government) is awaiting construction. There are 109 other energy sites within 10 km, 22 of them battery storage sites (hybrid battery and solar sites included). The register holds no incident at this site. It holds 14 incidents at battery storage sites (hybrid battery and solar sites included) in the United Kingdom, and 199 worldwide.

WHIRLWIND ENERGY STORAGE LIMITED (12314124), active, since 2019. No outstanding charges on the register. Members see the charges register: each charge, when it was created and the lender it is in favour of.

Source: Companies House, matched by the operator's name. If this is the wrong company, tell the editor.

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack for West Boldon Substation - Battery Energy Storage sets out every comparable incident for this project, with sources. £295, by email in minutes; the order form arrives filled in from this record.

Get the evidence pack for this site, £295 See a sample pack (PDF)

The pack for this site lists 5 comparable battery incidents in the United Kingdom, grid-scale only, nearest first. The nearest is EIR-0638, Explosion and prolonged fire at Orsted battery storage site in Liverpool, 196 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-06382020Explosion and prolonged fire at Orsted battery storage site in Liverpool196 kmMajor
EIR-05842026Fire in a battery container at Rufford Colliery BESS, Rainworth; owner attributes it to a short circuit in NMC cells204 kmSignificant
EIR-00582025Fire in two battery containers at Cirencester Hybrid Solar Farm, Gloucestershire360 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 2 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack
Technology
Battery storage (Stand-alone Storage)
Capacity
60 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Awaiting Construction (Appeal Granted)
Operator or applicant
Whirlwind Energy Storage Limited
Location
East of the West Boldon Substation, 400 metres south of the A184 and 300m East of the A189 in South Tyneside, Tyne And Wear, NE35 9PE, United Kingdom
Planning authority
South Tyneside
Planning application
ST/0486/23/FUL
Appeal reference
APP/A4520/W/24/3350689

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for ST/0486/23/FUL, with what the planning evidence pack adds for this site.

Every application in South Tyneside · Alerts for applications and incidents near here

  • 17 July 2023 Planning application submitted
  • 21 June 2024 Planning permission refused
  • 20 September 2024 Appeal lodged
  • 10 December 2024 Planning permission granted
  • 10 December 2024 Appeal granted
  • 10 December 2027 Planning permission runs out

None found. The register holds no published incident that names West Boldon Substation - Battery Energy Storage. If you know of one, report it (confidential reports are anonymised).

Has West Boldon Substation - Battery Energy Storage had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names West Boldon Substation - Battery Energy Storage; it holds 14 incidents at battery storage sites (hybrid battery and solar sites included) in the United Kingdom.
What is the status of West Boldon Substation - Battery Energy Storage?
Awaiting Construction, in the Renewable Energy Planning Database (UK government), where it last changed on 15 July 2025.
Where is West Boldon Substation - Battery Energy Storage?
In The Boldons, Tyne And Wear, United Kingdom (postcode NE35 9PE).

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).