Vestry Road

Awaiting Construction1.5 MWChecked 6 October 2026Last changed in the dataset 5 August 2020

Technology
Onshore wind
Capacity
1.5 MW
Status
Awaiting Construction (Appeal Granted)
Operator or applicant
Hill Power
Location
553 Metres South East Of No, 4 Vestry Cladymore, Mowhan, Armagh, Co Armagh, Co. Armagh, BT60, United Kingdom
Planning authority
Armagh City, Banbridge and Craigavon
Planning application
LA08/2018/1648/F
Appeal reference
2019/A0033
Turbines
1, 100 m to tip

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 21 November 2018 Planning application submitted
  • 17 May 2019 Appeal lodged
  • 6 January 2020 Planning permission granted
  • 6 January 2020 Planning permission refused
  • 6 January 2020 Appeal granted
  • 5 January 2025 Planning permission expired

None found. The register holds no published incident that names Vestry Road. If you know of one, report it (confidential reports are anonymised).

The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.

What fails at onshore wind farms

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.