Awaiting Construction49.9 MWChecked 6 October 2026Last changed in the dataset 3 March 2026

Technology
Solar
Capacity
49.9 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
PACE Elevate Energy Limited
Location
E/O Twinwood Road Oakley And Clapham, Se/O Thurleigh Road, Milton Ernest And Thurleigh, Bedford, Bedfordshire, MK41 6BL, United Kingdom
Planning authority
Bedford
Planning application
25/01292/MAF

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 4 July 2025 Planning application submitted
  • 19 February 2026 Planning permission granted
  • 19 February 2029 Planning permission expired

None found. The register holds no published incident that names Twinwood Road Oakley And Clapham, Thurleigh Road - Solar Farm. If you know of one, report it (confidential reports are anonymised).

The register holds 86 incidents at solar farms in the United Kingdom, 59 of them fires, and 344 worldwide. Counts of incidents in published reporting, not rates.

What fails at solar farms · All solar farms incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.