← Back to South Yorkshire

Energy sites / United Kingdom / South Yorkshire

Battery storage · United Kingdom

Tofts Lane

Planning Permission Expired40 MWChecked 6 October 2026Last changed in the dataset 27 May 2020

Technology
Battery storage (Stand-alone Storage)
Capacity
40 MW
Status
Planning Permission Expired
Operator or applicant
Enstor Power UK
Location
Tofts Lane, Snowden Hill, Barnsley, South Yorkshire, S36 8YR, United Kingdom
Planning authority
Barnsley
Planning application
2017/0624

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 3 May 2017 Planning application submitted
  • 21 July 2017 Planning permission granted
  • 7 September 2020 Planning permission expired

None found. The register holds no published incident that names Tofts Lane. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.