Tanners Lane - Battery Energy Storage Facility (Phase One)

Awaiting Construction40 MWChecked 6 October 2026Last changed in the dataset 7 April 2022

Technology
Battery storage (Stand-alone Storage)
Capacity
40 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
British Solar Renewables
Location
Newlands Farm Tanners Lane Fareham, Hampshire, PO14 1BL, United Kingdom
Planning authority
Fareham
Planning application
P/19/1019/FP

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 2 September 2019 Planning application submitted
  • 26 November 2019 Planning permission granted
  • 26 November 2022 Planning permission expired

None found. The register holds no published incident that names Tanners Lane - Battery Energy Storage Facility (Phase One). If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.