South Park Solar Farm

Awaiting Construction15 MWChecked 6 October 2026Last changed in the dataset 8 October 2024

Technology
Solar
Capacity
15 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
Renewable Connections Developments Limited
Location
South Park Farm, Andover Lane, Great Shoddesden, Andover, Hampshire, SP11 9LP, United Kingdom
Planning authority
Test Valley
Planning application
21/02997/FULLN

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 12 October 2021 Planning application submitted
  • 3 November 2022 Planning permission granted
  • 3 November 2025 Planning permission expired

None found. The register holds no published incident that names South Park Solar Farm. If you know of one, report it (confidential reports are anonymised).

The register holds 86 incidents at solar farms in the United Kingdom, 59 of them fires, and 344 worldwide. Counts of incidents in published reporting, not rates.

What fails at solar farms · All solar farms incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.