← Back to Somerset
Planning pack for this site, £295Other options

Battery storage · United Kingdom

Smithyard Lane - Battery Storage

Operator Conrad Energy Limited

Awaiting Construction15 MWData checked 16 November 2026Source record dated 9 March 2022

Watch this siteIts outage notices and incidents, what it earns and where it ranks, in your workspace and by email. 7 days free, no card.

Smithyard Lane - Battery Storage is a 15 MW battery storage site 11 km south-east of Minehead, Somerset, United Kingdom. Its planning application (3/39/22/007) went to Somerset on 23 February 2022 and was granted on 15 February 2023. Its status in the Renewable Energy Planning Database (UK government) is awaiting construction. There are 9 other energy sites within 10 km, 3 of them battery storage sites (hybrid battery and solar sites included). The register holds no incident at this site. It holds 14 incidents at battery storage sites (hybrid battery and solar sites included) in the United Kingdom, and 199 worldwide.

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack for Smithyard Lane - Battery Storage sets out every comparable incident for this project, with sources. £295, by email in minutes; the order form arrives filled in from this record.

Get the evidence pack for this site, £295 See a sample pack (PDF)

The pack for this site lists 5 comparable battery incidents in the United Kingdom, grid-scale only, nearest first. The nearest is EIR-0249, Smoke and fire incident at Battery Box, Pinhoe Road, Exeter, 49 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-02492026Smoke and fire incident at Battery Box, Pinhoe Road, Exeter49 kmSignificant
EIR-00582025Fire in two battery containers at Cirencester Hybrid Solar Farm, Gloucestershire115 kmSignificant
EIR-06382020Explosion and prolonged fire at Orsted battery storage site in Liverpool249 kmMajor
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 2 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack
Technology
Battery storage (Stand-alone Storage)
Capacity
15 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
Conrad Energy Limited
Location
adjacent to Gas Substation, Smithyard Lane, Williton, Somerset, TA23 0NA, United Kingdom
Planning authority
Somerset
Planning application
3/39/22/007

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for 3/39/22/007, with what the planning evidence pack adds for this site.

Every application in Somerset · Alerts for applications and incidents near here

  • 23 February 2022 Planning application submitted
  • 15 February 2023 Planning permission granted
  • 15 February 2026 Planning permission expired

None found. The register holds no published incident that names Smithyard Lane - Battery Storage. If you know of one, report it (confidential reports are anonymised).

Has Smithyard Lane - Battery Storage had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names Smithyard Lane - Battery Storage; it holds 14 incidents at battery storage sites (hybrid battery and solar sites included) in the United Kingdom.
What is the status of Smithyard Lane - Battery Storage?
Awaiting Construction, in the Renewable Energy Planning Database (UK government), where it last changed on 9 March 2022.
Where is Smithyard Lane - Battery Storage?
11 km south-east of Minehead, Somerset, United Kingdom (postcode TA23 0NA).