Pinnacle Storage Park, Dale Abbey - Solar PV Panels

Under Construction1 MWChecked 6 October 2026Last changed in the dataset 19 April 2022

Technology
Solar
Capacity
1 MW
Status
Under Construction
Operator or applicant
Hansteen Property Investments
Location
Unit 114 & Unit 116, Pinnacle Storage Park, Adj Jubilee House, Cat & Fiddle Lane, Dale Abbey, Derbyshire, DE7 6HE, United Kingdom
Planning authority
Erewash
Planning application
0322/0080

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 18 March 2022 Planning application submitted
  • 7 July 2022 Planning permission granted
  • 1 January 2023 Construction started

None found. The register holds no published incident that names Pinnacle Storage Park, Dale Abbey - Solar PV Panels. If you know of one, report it (confidential reports are anonymised).

The register holds 86 incidents at solar farms in the United Kingdom, 59 of them fires, and 344 worldwide. Counts of incidents in published reporting, not rates.

What fails at solar farms · All solar farms incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.