Solar · United Kingdom

Perrinpit Farm

Under Construction49.9 MWChecked 6 October 2026Last changed in the dataset 5 August 2025

Technology
Solar
Capacity
49.9 MW
Status
Under Construction
Operator or applicant
Grune Energien
Location
Land At Perrinpit Farm, Perrinpit Road, Frampton Cotterell, Bristol, Avon, Gloucestershire, BS36 2AT, United Kingdom
Planning authority
South Gloucestershire
Planning application
P21/01624/F

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 12 March 2021 Planning application submitted
  • 21 September 2022 Planning permission granted
  • 1 June 2025 Construction started

None found. The register holds no published incident that names Perrinpit Farm. If you know of one, report it (confidential reports are anonymised).

The register holds 86 incidents at solar farms in the United Kingdom, 59 of them fires, and 344 worldwide. Counts of incidents in published reporting, not rates.

What fails at solar farms · All solar farms incidents