Nether Moor Field

Operational49.9 MWChecked 6 October 2026Last changed in the dataset 27 May 2020

Technology
Battery storage (Stand-alone Storage)
Capacity
49.9 MW
Status
Operational
Operator or applicant
Thurcroft Energy (Max Design Consultancy)
Location
Nether Moor Field, Green Lane, Thurcroft, Rotherham, South Yorkshire, South Yorkshire, S66, United Kingdom
Planning authority
Rotherham
Planning application
RB2017/1426
First operating
2020

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 29 September 2017 Planning application submitted
  • 21 December 2017 Planning permission granted
  • 1 September 2020 Operational

None found. The register holds no published incident that names Nether Moor Field. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 176 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.