Under Construction50 MWChecked 6 October 2026Last changed in the dataset 6 March 2026

Technology
Battery storage (Stand-alone Storage)
Capacity
50 MW
Status
Under Construction
Operator or applicant
Statkraft UK LTD
Location
Site 400 metres North West of Sergeantlaw, Gleniffer Road, Paisley, Renfrewshire, PA1, United Kingdom
Planning authority
Renfrewshire
Planning application
21/0034/PP

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 21 January 2021 Planning application submitted
  • 5 November 2021 Planning permission refused
  • 7 February 2022 Appeal lodged
  • 28 April 2022 Planning permission granted
  • 28 April 2022 Appeal granted
  • 29 August 2023 Construction started

None found. The register holds no published incident that names Neilston Greener Grid Park. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.