National Grid Enderby Substation

Operational57 MWChecked 6 October 2026Last changed in the dataset 6 March 2026

Technology
Battery storage (Stand-alone Storage)
Capacity
57 MW
Status
Operational
Operator or applicant
Gore Street
Location
National Grid Land To North Of, Desford Road, Enderby, Leicester, Leicestershire, Leicestershire, LE19 4AD, United Kingdom
Planning authority
Blaby
Planning application
20/0896/FUL
First operating
2025

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 28 August 2020 Planning application submitted
  • 4 February 2021 Planning permission granted
  • 1 January 2023 Construction started
  • 1 February 2025 Operational

None found. The register holds no published incident that names National Grid Enderby Substation. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.