Battery storage · United Kingdom

Enderby Storage, Redcomb Farm

Operational49.9 MWChecked 6 October 2026Last changed in the dataset 6 March 2026

Technology
Battery storage (Stand-alone Storage)
Capacity
49.9 MW
Status
Operational
Operator or applicant
Statera Energy / Gresham House
Location
Land Opposite Redcomb Farm, Desford Road, Lubbesthorpe, Leicester, Leicestershire, Leicestershire, LE19 4AD, United Kingdom
Planning authority
Blaby
Planning application
17/1223/FUL
First operating
2022

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 13 October 2017 Planning application submitted
  • 4 January 2018 Planning permission granted
  • 1 April 2021 Construction started
  • 1 January 2022 Operational

None found. The register holds no published incident that names Enderby Storage, Redcomb Farm. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.