Onshore wind · United Kingdom
Mynydd Y Gwair Wind Farm
Operator RWE Npower Renewables& Innogy
Operational32.8 MWData checked 16 November 2026Source record dated 30 April 2019
Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.
Mynydd Y Gwair Wind Farm is a 32.8 MW wind farm 5.9 km south-east of Ammanford, West Glamorgan, United Kingdom. Its planning application (2012/1221) went to Swansea on 11 September 2012 and was granted on 8 February 2013. It has been operating since 24 April 2019. Its status in the Renewable Energy Planning Database (UK government) is operational. There are 39 other energy sites within 10 km, 5 of them wind farms. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.
Get an email when Mynydd Y Gwair Wind Farm changes
Free. An email when its status changes: a planning decision, building starting, going live or closing. And each Monday, onshore wind incidents in the United Kingdom. No account needed; unsubscribe in one click.
Confirm your email and every wind turbine incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Members see the sites and incidents around this one, and every record behind them.
The site
- Technology
- Onshore wind
- Capacity
- 32.8 MW
- Capacity figure from
- Renewable Energy Planning Database (UK government)
- Status
- Operational
- Operator or applicant
- RWE Npower Renewables& Innogy
- Location
- Swansea, West Glamorgan, United Kingdom
- Planning authority
- Swansea
- Planning application
- 2012/1221
- First operating
- 2019
- Turbines
- 16
View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.
The planning application page for 2012/1221, with what the planning evidence pack adds for this site.
Every application in Swansea · Alerts for applications and incidents near here
Timeline
- 11 September 2012 Planning application submitted
- 8 February 2013 Planning permission granted
- 8 February 2017 Construction started
- 24 April 2019 Operational
Incidents on the register at this site
None found. The register holds no published incident that names Mynydd Y Gwair Wind Farm. If you know of one, report it (confidential reports are anonymised).
Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.
Questions
- Has Mynydd Y Gwair Wind Farm had a fire or other incident?
- None is on the register as of 21 November 2026. The register holds no published incident that names Mynydd Y Gwair Wind Farm; it holds 63 incidents at wind farms in the United Kingdom.
- What is the status of Mynydd Y Gwair Wind Farm?
- Operational, in the Renewable Energy Planning Database (UK government), where it last changed on 30 April 2019.
- Where is Mynydd Y Gwair Wind Farm?
- 5.9 km south-east of Ammanford, West Glamorgan, United Kingdom.
Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).