← Back to Gwent
Planning pack for this site, £295Other options

Onshore wind · United Kingdom

Mynydd Llanhilleth - Wind Farm

Operator Pennant Walters · Owner G. Walters (Holdings) Limited

Revised34 MWData checked 16 November 2026Source record dated 26 September 2025

Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.

Mynydd Llanhilleth - Wind Farm is a 34 MW wind farm on the edge of Crumlin, Gwent, United Kingdom. Its planning application (DNS/3273368) went to Welsh Government (NSIP) on 9 August 2023 and was withdrawn on 21 June 2024. Its status in the Renewable Energy Planning Database (UK government) is revised. There are 31 other energy sites within 10 km, 12 of them wind farms. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.

PENNANT WALTERS (HOLDINGS) LIMITED (05633297), active, since 2005. 2 outstanding charges on the register. Members see the charges register: each charge, when it was created and the lender it is in favour of.

Source: Companies House, matched by the operator's name. If this is the wrong company, tell the editor.

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack for Mynydd Llanhilleth - Wind Farm sets out every comparable incident for this project, with sources. £295, by email in minutes; the order form arrives filled in from this record.

Get the evidence pack for this site, £295 See a sample pack (PDF)

The pack for this site lists 49 comparable onshore wind incidents in the United Kingdom, nearest first. The nearest is EIR-0794, Wind turbine collapses at Pant-y-Wal wind farm near Gilfach Goch, 25 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-07942022Wind turbine collapses at Pant-y-Wal wind farm near Gilfach Goch25 kmSignificant
EIR-08742026Turbine blade detaches at RWE's Brechfa Forest West wind farm in Wales77 kmSignificant
EIR-07902022Nordex attributes a Welsh wind turbine collapse to an overspeed condition77 kmMajor
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 46 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack
Technology
Onshore wind
Capacity
34 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Revised
Operator or applicant
Pennant Walters
Owner
G. Walters (Holdings) Limited
Location
Mynydd Llanhilleth Wind Farm, Mynydd Llanhilleth Common, Pontypool, Gwent, NP4, United Kingdom
Planning authority
Welsh Government (NSIP)
Planning application
DNS/3273368
Turbines
8, 180 m to tip

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for DNS/3273368, with what the planning evidence pack adds for this site.

Every application in Welsh Government (NSIP) · Alerts for applications and incidents near here

  • 9 August 2023 Planning application submitted
  • 21 June 2024 Application withdrawn

None found. The register holds no published incident that names Mynydd Llanhilleth - Wind Farm. If you know of one, report it (confidential reports are anonymised).

Has Mynydd Llanhilleth - Wind Farm had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names Mynydd Llanhilleth - Wind Farm; it holds 63 incidents at wind farms in the United Kingdom.
What is the status of Mynydd Llanhilleth - Wind Farm?
Revised, in the Renewable Energy Planning Database (UK government), where it last changed on 26 September 2025.
Where is Mynydd Llanhilleth - Wind Farm?
On the edge of Crumlin, Gwent, United Kingdom (postcode NP4).

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).