Lethen Wind Farm Wind Turbines and Energy Storage

Application Refused10 MWChecked 6 October 2026Last changed in the dataset 10 April 2024

Technology
Battery storage (Co-located with RE)
Capacity
10 MW
Status
Application Refused (Planning Permission Refused)
Operator or applicant
Fred Olsen Renewables Ltd
Location
Land 4700M NW Of Gamekeepers Cottage Nairn, Highland, IV12, United Kingdom
Planning authority
Scottish Government (S36)
Planning application
ECU00002216

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 21 January 2022 Planning application submitted
  • 23 February 2024 Planning permission refused

None found. The register holds no published incident that names Lethen Wind Farm Wind Turbines and Energy Storage. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 176 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.