Battery storage · United Kingdom

Kells Substation

Awaiting ConstructionChecked 6 October 2026Last changed in the dataset 21 April 2020

Technology
Battery storage (Stand-alone Storage)
Status
Awaiting Construction (Appeal Granted)
Operator or applicant
Kells Bes (ABO Wind)
Location
Lands at, Doagh Road, Approximately 137m North East, Dungannon, Co. Tyrone, BT71 5BJ, United Kingdom
Planning authority
Antrim and Newtownabbey
Planning application
LA03/2018/0984/F
Appeal reference
2018/A0248

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 25 October 2018 Planning application submitted
  • 22 March 2019 Planning permission refused
  • 27 March 2019 Appeal lodged
  • 27 November 2019 Planning permission granted
  • 27 November 2019 Appeal granted
  • 27 November 2024 Planning permission expired

None found. The register holds no published incident that names Kells Substation. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.