← Back to Wiltshire

Energy sites / United Kingdom / Wiltshire

Solar · United Kingdom

Forest Gate - Solar Farm & Battery Storage

Awaiting Construction49.9 MWChecked 6 October 2026Last changed in the dataset 28 June 2021

Technology
Solar
Capacity
49.9 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
Eden Renewables
Location
Forest Gate, Pewsham, Chippenham, Wiltshire, SN15 3RS, United Kingdom
Planning authority
Wiltshire
Planning application
PL/2021/06112

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 11 June 2021 Planning application submitted
  • 10 March 2023 Planning permission granted
  • 10 March 2026 Planning permission expired

None found. The register holds no published incident that names Forest Gate - Solar Farm & Battery Storage. If you know of one, report it (confidential reports are anonymised).

The register holds 86 incidents at solar farms in the United Kingdom, 59 of them fires, and 344 worldwide. Counts of incidents in published reporting, not rates.

What fails at solar farms · All solar farms incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.