← Back to Devon

Energy sites / United Kingdom / Devon

Solar · United Kingdom

Ford Oaks Solar & Green Infrastructure Facility

Under Construction30 MWChecked 6 October 2026Last changed in the dataset 17 February 2026

Technology
Solar
Capacity
30 MW
Status
Under Construction
Operator or applicant
Low Carbon Alliance / Taiyo Power & Storage
Location
Marsh Green Farm Marsh Green, Exeter, Devon, EX5 2EU, United Kingdom
Planning authority
East Devon
Planning application
22/0990/MFUL
Appeal reference
APP/U1105/W/23/3320714

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 19 May 2022 Planning application submitted
  • 12 January 2023 Planning permission refused
  • 20 April 2023 Appeal lodged
  • 30 November 2023 Planning permission granted
  • 30 November 2023 Appeal granted
  • 1 October 2025 Construction started
  • 30 November 2026 Planning permission expired

None found. The register holds no published incident that names Ford Oaks Solar & Green Infrastructure Facility. If you know of one, report it (confidential reports are anonymised).

The register holds 86 incidents at solar farms in the United Kingdom, 59 of them fires, and 344 worldwide. Counts of incidents in published reporting, not rates.

What fails at solar farms · All solar farms incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.