Costa Head Wind Farm

Operator Hoolan Energy

Awaiting Construction16.3 MWData checked 16 November 2026Source record dated 5 August 2020

Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.

Costa Head Wind Farm is a 16.3 MW wind farm 24 km north-west of Kirkwall, Orkney Islands, United Kingdom. Its planning application (16/580/TPPMAJ) went to Orkney Islands on 9 December 2016 and was granted on appeal on 18 April 2019. Its status in the Renewable Energy Planning Database (UK government) is awaiting construction. There are 9 other energy sites within 10 km. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack for Costa Head Wind Farm sets out every comparable incident for this project, with sources. £295, by email in minutes; the order form arrives filled in from this record.

Get the evidence pack for this site, £295 See a sample pack (PDF)

The pack for this site lists 49 comparable onshore wind incidents in the United Kingdom, nearest first. The nearest is EIR-2512, Fire at Viking Wind Farm construction site on Shetland, 169 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-25122023Fire at Viking Wind Farm construction site on Shetland169 kmMinor
EIR-12912022Fatality at Viking wind farm site in Shetland Islands169 kmMajor
EIR-07672024Nordex turbine fire prompts investigation at Scottish wind farm268 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 46 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack
Technology
Onshore wind
Capacity
16.3 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Awaiting Construction (Appeal Granted)
Operator or applicant
Hoolan Energy
Location
Costa Head, on the north coast of Orkney Mainland, Orkney Islands, KW17 2NP, United Kingdom
Planning authority
Orkney Islands
Planning application
16/580/TPPMAJ
Appeal reference
PPA-330-2022
Turbines
5, 125 m to tip

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for 16/580/TPPMAJ, with what the planning evidence pack adds for this site.

Every application in Orkney Islands · Alerts for applications and incidents near here

  • 9 December 2016 Planning application submitted
  • 21 September 2018 Planning permission refused
  • 8 October 2018 Appeal lodged
  • 18 April 2019 Planning permission granted
  • 18 April 2019 Appeal granted
  • 11 April 2027 Planning permission runs out

None found. The register holds no published incident that names Costa Head Wind Farm. If you know of one, report it (confidential reports are anonymised).

Has Costa Head Wind Farm had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names Costa Head Wind Farm; it holds 63 incidents at wind farms in the United Kingdom.
What is the status of Costa Head Wind Farm?
Awaiting Construction, in the Renewable Energy Planning Database (UK government), where it last changed on 5 August 2020.
Where is Costa Head Wind Farm?
24 km north-west of Kirkwall, Orkney Islands, United Kingdom (postcode KW17 2NP).

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).