← Back to Dyfed

Energy sites / United Kingdom / Dyfed

Battery storage · United Kingdom

Castle Quarry - Micro Energy Storage

Awaiting Construction0.2 MWChecked 6 October 2026Last changed in the dataset 18 November 2025

Technology
Battery storage (Stand-alone Storage)
Capacity
0.2 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
AMP Clean Energy
Location
Btw Castle Quarry And Haven Court, Pembroke, Dyfed, SA71 4JB, United Kingdom
Planning authority
Pembrokeshire
Planning application
25/0355/PA

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 28 July 2025 Planning application submitted
  • 22 September 2025 Planning permission granted
  • 21 September 2030 Planning permission expired

None found. The register holds no published incident that names Castle Quarry - Micro Energy Storage. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents