Awaiting Construction150 MWData checked 16 November 2026Source record dated 8 January 2026

Watch this siteIts outage notices and incidents, what it earns and where it ranks, in your workspace and by email. 7 days free, no card.

Belston Battery Storage is a 150 MW battery storage site 4.9 km east of Ayr, United Kingdom. Its planning application (ECU00005141) went to Scottish Government (S36) on 28 November 2024 and was granted on 22 July 2025. Its status in the Renewable Energy Planning Database (UK government) is awaiting construction. There are 18 other energy sites within 10 km, 9 of them battery storage sites (hybrid battery and solar sites included). The register holds no incident at this site. It holds 14 incidents at battery storage sites (hybrid battery and solar sites included) in the United Kingdom, and 199 worldwide.

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack for Belston Battery Storage sets out every comparable incident for this project, with sources. £295, by email in minutes; the order form arrives filled in from this record.

Get the evidence pack for this site, £295 See a sample pack (PDF)

The pack for this site lists 5 comparable battery incidents in the United Kingdom, grid-scale only, nearest first. The nearest is EIR-0638, Explosion and prolonged fire at Orsted battery storage site in Liverpool, 252 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-06382020Explosion and prolonged fire at Orsted battery storage site in Liverpool252 kmMajor
EIR-05842026Fire in a battery container at Rufford Colliery BESS, Rainworth; owner attributes it to a short circuit in NMC cells342 kmSignificant
EIR-00582025Fire in two battery containers at Cirencester Hybrid Solar Farm, Gloucestershire450 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 2 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack
Technology
Battery storage (Stand-alone Storage)
Capacity
150 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
KX Alpha Ltd
Location
north of A70 at Belston, Ayrshire, KA6 5JD, United Kingdom
Planning authority
Scottish Government (S36)
Planning application
ECU00005141

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for ECU00005141, with what the planning evidence pack adds for this site.

Every application in Scottish Government (S36) · Alerts for applications and incidents near here

  • 28 November 2024 Planning application submitted
  • 22 July 2025 Planning permission granted
  • 22 July 2028 Planning permission runs out

None found. The register holds no published incident that names Belston Battery Storage. If you know of one, report it (confidential reports are anonymised).

Has Belston Battery Storage had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names Belston Battery Storage; it holds 14 incidents at battery storage sites (hybrid battery and solar sites included) in the United Kingdom.
What is the status of Belston Battery Storage?
Awaiting Construction, in the Renewable Energy Planning Database (UK government), where it last changed on 8 January 2026.
Where is Belston Battery Storage?
4.9 km east of Ayr, United Kingdom (postcode KA6 5JD).