Onshore wind · United Kingdom
Avonmouth Wind Power
Operator Wessex Water Engineering Services
Operational8.2 MWData checked 16 November 2026Source record dated 27 February 2014
Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.
Avonmouth Wind Power is a 8.2 MW wind farm 7.4 km north-east of Portishead, Avon, United Kingdom. Its planning application (08/04925/F) went to Bristol, City of on 8 December 2008 and was granted on 25 March 2009. It has been operating since 6 February 2014. Its status in the Renewable Energy Planning Database (UK government) is operational. There are 78 other energy sites within 10 km, 6 of them wind farms. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.
Get an email when Avonmouth Wind Power changes
Free. An email when its status changes: a planning decision, building starting, going live or closing. And each Monday, onshore wind incidents in the United Kingdom. No account needed; unsubscribe in one click.
Confirm your email and every wind turbine incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Members see the sites and incidents around this one, and every record behind them.
The site
- Technology
- Onshore wind
- Capacity
- 8.2 MW
- Capacity figure from
- Renewable Energy Planning Database (UK government)
- Status
- Operational
- Operator or applicant
- Wessex Water Engineering Services
- Location
- Bristol Sewage Treatment Work, Bristol, BS11 0YS, Avon, United Kingdom
- Planning authority
- Bristol, City of
- Planning application
- 08/04925/F
- First operating
- 2014
- Turbines
- 4
View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.
The planning application page for 08/04925/F, with what the planning evidence pack adds for this site.
Every application in Bristol, City of · Alerts for applications and incidents near here
Timeline
- 8 December 2008 Planning application submitted
- 25 March 2009 Planning permission granted
- 3 December 2012 Construction started
- 6 February 2014 Operational
Incidents on the register at this site
None found. The register holds no published incident that names Avonmouth Wind Power. If you know of one, report it (confidential reports are anonymised).
Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.
Questions
- Has Avonmouth Wind Power had a fire or other incident?
- None is on the register as of 21 November 2026. The register holds no published incident that names Avonmouth Wind Power; it holds 63 incidents at wind farms in the United Kingdom.
- What is the status of Avonmouth Wind Power?
- Operational, in the Renewable Energy Planning Database (UK government), where it last changed on 27 February 2014.
- Where is Avonmouth Wind Power?
- 7.4 km north-east of Portishead, Avon, United Kingdom.
Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).