A minor explosion occurred at the Al-Raas M (Head M) main transformer station during maintenance work, causing a power outage that affected parts of Salmiya, Kuwait. The incident resulted in the loss of approximately 25 megawatts of electricity supply to the...
Ministry of Electricity
Named in a role in 1 record, and mentioned in the text of 4 entries, in 2023.
Being named is not a finding of fault. Counts are of records in published reporting, not rates, and the company's role is the one the sources give.
Work at Ministry of Electricity? See every record that names it, free, and ask for a correction or add your side.
Records naming this company
Free entries that mention Ministry of Electricity
A fire occurred at the 132 kV Al-Bakr substation in Basra on 30 July 2023 at about 12:40. The Ministry of Electricity said the fire disconnected transmission lines between the southern and central regions, caused frequency oscillations and tripped generation...
A single report, quoting Kuwait’s Ministry of Electricity and Water, says an explosion occurred at a main electrical transformer in Salmiya during periodical maintenance. The blast caused a fire and injured four people, and a partial power outage affected the...
See what failed, why, and what it cost
The record behind each entry: the manufacturer, integrator and operator, root cause, failure mode, downtime, losses and every source.
A fire broke out in the feeder cell of transformer No. 1 at a main electricity substation in the Hawally region, known as Hawally B, on 8 April 2020. The fire caused a power outage across the block the substation supplies. The Ministry of Electricity and...
What this page is, and what it is not
It counts the records in this register that name this company in any role. Being named is not a finding of fault. Most incidents have several contributing causes, and the company named as manufacturer, integrator, operator or contractor is often not the cause of what went wrong.
Counts reflect what public reporting names, so a company with a large installed base, or one operating where reporting is open, will appear more often than a company of the same size elsewhere. Read the counts alongside the note on coverage in the methodology.
If you work for this company and something here is wrong, tell us and we will correct it. Use the corrections page: we acknowledge within 2 working days and decide within 10.