← Back to the applications
Full planning pack, launch price £145Other options

Planning application · Onshore wind · Scottish Government (S36)

Pauls Hill 2

Awaiting Construction28 MWApplication ECU00000578Submitted 29 March 2018Granted on appeal 11 December 2020

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
ECU00000578
Planning authority
Scottish Government (S36)
County or area
Grampian
Nation
Scotland
Technology
Onshore wind
Capacity
28 MW
Status
Awaiting Construction (Appeal Granted)
Operator or applicant
Fred Olsen Renewables
Location
Paul's Hill, Bowlingalloch, Moray
Appeal reference
WIN-300-3
Turbines
7, 150 m to tip
  • 29 March 2018 Planning application submitted
  • 20 December 2018 Appeal lodged
  • 11 December 2020 Planning permission granted
  • 11 December 2020 Appeal granted

The pack for this site lists 43 comparable onshore wind incidents in the United Kingdom, nearest first. The nearest is EIR-0767, Nordex turbine fire prompts investigation at Scottish wind farm, 83 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-07672024Nordex turbine fire prompts investigation at Scottish wind farm83 kmSignificant
EIR-13862022Wind turbine fire near St Cyrus in Aberdeenshire98 kmMinor
EIR-04412025Wind turbine collapses at Aviva's Pitheavlis site in Perth117 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 40 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near Pauls Hill 2 is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in Scottish Government (S36).

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.