Full planning pack, launch price £145Other options

Planning application · Battery storage · Warwick

Holly Lane Energy Park - Solar Farm & Battery Storage

Awaiting Construction75 MWApplication W/23/1358Submitted 14 September 2023Granted on appeal 30 January 2025

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
W/23/1358
Planning authority
Warwick
County or area
West Midlands
Nation
England
Technology
Battery storage (Co-located with RE)
Capacity
75 MW
Status
Awaiting Construction (Appeal Granted)
Operator or applicant
Exagen
Location
Holly Lane Energy Park, B37 7AN
Appeal reference
APP/T3725/W/24/3347315
  • 14 September 2023 Planning application submitted
  • 23 April 2024 Planning permission refused
  • 1 July 2024 Appeal lodged
  • 30 January 2025 Planning permission granted
  • 30 January 2025 Appeal granted
  • 30 January 2030 Planning permission expired Date as recorded in the register

The pack for this site lists 5 comparable battery incidents in the United Kingdom, grid-scale only, nearest first. The nearest is EIR-0058, Fire in two battery containers at Cirencester Hybrid Solar Farm, Gloucestershire, 75 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-00582025Fire in two battery containers at Cirencester Hybrid Solar Farm, Gloucestershire75 kmSignificant
EIR-05842026Fire in a battery container at Rufford Colliery BESS, Rainworth, caused by a short circuit in NMC cells90 kmSignificant
EIR-06382020Explosion and prolonged fire at Orsted battery storage site in Liverpool144 kmMajor
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 2 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near B37 7AN is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in Warwick.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.