← Back to the applications
Full planning pack, launch price £145Other options

Planning application · Onshore wind · Aberdeenshire

Ferniebrae Barras - Wind turbine

Awaiting Construction0.3 MWApplication APP/2024/2094Submitted 19 December 2024Granted 24 December 2025

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
APP/2024/2094
Planning authority
Aberdeenshire
Nation
Scotland
Technology
Onshore wind
Capacity
0.3 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
CWE V27 Limited
Location
North East Of Ferniebrae Barras, AB39 2XU
Turbines
1, 75 m to tip
  • 19 December 2024 Planning application submitted
  • 24 December 2025 Planning permission granted
  • 24 December 2028 Planning permission expired Date as recorded in the register

The pack for this site lists 43 comparable onshore wind incidents in the United Kingdom, nearest first. The nearest is EIR-1386, Wind turbine fire near St Cyrus in Aberdeenshire, 18 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-13862022Wind turbine fire near St Cyrus in Aberdeenshire18 kmMinor
EIR-04412025Wind turbine collapses at Aviva's Pitheavlis site in Perth91 kmSignificant
EIR-07672024Nordex turbine fire prompts investigation at Scottish wind farm112 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 40 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near AB39 2XU is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in Aberdeenshire.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.