← Back to the applications
Full planning pack, launch price £145Other options

Planning application · Battery storage · Tewkesbury

Brockworth Road - Battery Storage System

Awaiting Construction20 MWApplication 23/01078/FULSubmitted 24 November 2023Granted 25 April 2024

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
23/01078/FUL
Planning authority
Tewkesbury
County or area
Gloucestershire
Nation
England
Technology
Battery storage (Stand-alone Storage)
Capacity
20 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
Exagen
Location
W/O Brockworth Road, N/O The A417 & E/O M5, Gloucester, GL3 4WN
  • 25 April 2014 Planning permission expired
  • 24 November 2023 Planning application submitted
  • 25 April 2024 Planning permission granted

The pack for this site lists 5 comparable battery incidents in the United Kingdom, grid-scale only, nearest first. The nearest is EIR-0058, Fire in two battery containers at Cirencester Hybrid Solar Farm, Gloucestershire, 21 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-00582025Fire in two battery containers at Cirencester Hybrid Solar Farm, Gloucestershire21 kmSignificant
EIR-02492026Smoke and fire incident at Battery Box, Pinhoe Road, Exeter153 kmSignificant
EIR-05842026Fire in a battery container at Rufford Colliery BESS, Rainworth, caused by a short circuit in NMC cells159 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 2 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near GL3 4WN is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in Tewkesbury.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.