← Back to the applications
Full planning pack, launch price £145Other options

Planning application · Onshore wind · Scottish Government (S36)

Beinn Ghlas Wind Farm - Repowering

Application Submitted33.6 MWApplication 25/01240/PPSubmitted 27 August 2025

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
25/01240/PP
Planning authority
Scottish Government (S36)
County or area
Strathclyde
Nation
Scotland
Technology
Onshore wind
Capacity
33.6 MW
Status
Application Submitted (Planning Application Submitted)
Operator or applicant
Nadara Limited (Beaufort Wind Limited)
Location
Beinn Ghlas Wind Farm, Beinn Ghlas, Inveraray, PA35 1HY
Turbines
7, 149.9 m to tip
  • 27 August 2025 Planning application submitted

The pack for this site lists 43 comparable onshore wind incidents in the United Kingdom, nearest first. The nearest is EIR-0767, Nordex turbine fire prompts investigation at Scottish wind farm, 81 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-07672024Nordex turbine fire prompts investigation at Scottish wind farm81 kmSignificant
EIR-19512022Investigation begins after turbine fire at Ardrossan wind farm91 kmSignificant
EIR-11572026Fire destroys turbine at Whitelee windfarm near Glasgow93 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 40 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near PA35 1HY is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in Scottish Government (S36).

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.