← Back to the applications
Full planning pack, launch price £145Other options

Planning application · Onshore wind · West Lancashire

Barton House Farm, Pimbo Road - Wind Turbine

Awaiting Construction2.5 MWApplication 2024/1110/FULSubmitted 10 January 2025Granted 15 April 2026

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
2024/1110/FUL
Planning authority
West Lancashire
County or area
Greater Manchester
Nation
England
Technology
Onshore wind
Capacity
2.5 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
Green Energy Nationwide
Location
W/O Barton House Farm, Pimbo Road, West Pimbo, Skelmersdale, WN8 9PA
Turbines
1, 125 m to tip
  • 10 January 2025 Planning application submitted
  • 15 April 2026 Planning permission granted
  • 15 April 2029 Planning permission expired Date as recorded in the register

The pack for this site lists 43 comparable onshore wind incidents in the United Kingdom, nearest first. The nearest is EIR-0732, Nordex turbine damaged by suspected lightning strike at UK wind farm, 36 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-07322026Nordex turbine damaged by suspected lightning strike at UK wind farm36 kmMinor
EIR-16242026Crane topples on Scout Moor wind farm project39 kmMajor
EIR-08632017Fire destroys single turbine at Knabs Ridge wind farm near Harrogate96 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 40 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near WN8 9PA is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in West Lancashire.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.