Planned detonation removes damaged blade at Cross Winds wind farm
2026Published 28 Sept 2026Responsible editor: Chief Editor
- Where
- Cross Winds Energy Park near Akron, Tuscola County, Michigan
- Operator
- Consumers Energy
- What
- Damaged blade removed by planned detonation
- Cause
- Believed lightning strike several months earlier
Get the next one by email
Free alerts on wind (onshore) incidents in the United States, and an email when EIR-1479 is updated. No account needed; unsubscribe in one click.
Confirm your email and every wind turbine incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): Consumers Energy
What happened
A damaged wind turbine blade at the Cross Winds Energy Park near Akron in Tuscola County, Michigan, was removed by planned detonation on a Sunday evening. The site is operated by Consumers Energy. The blade had been damaged several months earlier and had been making noise when windy. Residents in the rural area had been notified in advance via social media that the detonation would take place between noon and 6 p.m., although the blast occurred later. The loud report was heard across the surrounding area.
Contributing factors
The blade is believed to have been damaged by a lightning strike several months earlier.
Lessons learned
- A lightning damaged blade left in place for months produced noise in wind, so operators should remove such blades without delay to avoid nuisance and further failure.
- Controlled detonation of a blade at height needs timed notice to residents, as the blast occurred later than stated and was heard across the area.
More lessons on weather and external hazards, structural integrity and turbines, from every incident on the register.
Not yet known
- Confirmed cause of the damage
- Turbine model and age
- Length of downtime
- Cost of the removal
This entry is updated when these are reported. Get an alert for the next one like it.
Source
Site page: Cross Winds Energy Park (status, dates and other incidents)
Published 2026-09-28. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.