Worker's hand amputated in machinery accident at Bango Wind Farm near Yass
Feb 2021Published 17 Sept 2026Responsible editor: Chief Editor
- Where
- Bango Wind Farm near Yass, New South Wales
- Owner
- CWP Renewables
- What
- Worker's hand severed on machinery
- Injuries
- Worker suffered severed hand
- Response
- SafeWork NSW opened investigation
Get the next one by email
Free alerts on wind (onshore) incidents in Australia, and an email when EIR-0939 is updated. No account needed; unsubscribe in one click.
Confirm your email and every wind turbine incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): CWP Renewables
What happened
A worker at the Bango Wind Farm construction site on Lachlan Valley Way near Yass, New South Wales, suffered a severed hand while working on machinery. The incident occurred on 4 February 2021 and the injured worker was airlifted to Royal North Shore Hospital in Sydney for treatment. SafeWork NSW, the state workplace safety regulator, attended the site and opened an investigation into the accident, stating the inquiry could take several months to complete.
The wind farm, comprising 45 turbines, was under construction at the time, having been approved in 2018 with construction beginning in 2019. CWP Renewables, the site's owner, declined to comment on the incident when approached by media.
Contributing factors
Not reported. The specific machinery involved and the circumstances leading to the amputation were not detailed in available reporting, and the regulatory investigation was ongoing at time of publication.
Lessons learned
- Machinery guarding and isolation must be verified on every item of equipment during wind farm construction when multiple contractors work on site.
- Remote wind farm sites need pre-planned air ambulance access so an injured worker can reach specialist care quickly.
More lessons on worker safety and safe systems of work, from every incident on the register.
Not yet known
- Specific machinery and failure mode
- Downtime and repair cost
- Investigation findings and recommendations
This entry is updated when these are reported. Get an alert for the next one like it.
Source
Site page: Bango (status, dates and other incidents)
Published 2026-09-17. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.