← Back to Warwickshire

Energy sites / United Kingdom / Warwickshire

Battery storage · United Kingdom

Weddington Road - Battery Energy Storage

Awaiting Construction49.9 MWChecked 6 October 2026Last changed in the dataset 10 July 2026

Technology
Battery storage (Stand-alone Storage)
Capacity
49.9 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
Fig Power
Location
Nuneaton Old Edwardians Rugby Football Club, Weddington Road, Nuneaton, Warwickshire, CV10 0AL, United Kingdom
Planning authority
Nuneaton and Bedworth
Planning application
40498

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 29 August 2024 Planning application submitted
  • 2 February 2026 Planning permission granted
  • 2 February 2029 Planning permission expired

None found. The register holds no published incident that names Weddington Road - Battery Energy Storage. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 176 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.