← Back to Cambridgeshire

Energy sites / United Kingdom / Cambridgeshire

Battery storage · United Kingdom

Weald Farm, Cambridge Road - Solar Farm & Battery Storage

Awaiting Construction50 MWChecked 6 October 2026Last changed in the dataset 19 February 2026

Technology
Battery storage (Co-located with RE)
Capacity
50 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
Ashfield District Council / Voltalia UK
Location
Ne/O Weald Farm, Cambridge Road, Eynesbury, St Neots, Cambridgeshire, PE19 6SR, United Kingdom
Planning authority
Huntingdonshire
Planning application
24/00295/FUL

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 5 April 2024 Planning application submitted
  • 8 May 2025 Planning permission granted
  • 8 May 2027 Planning permission expired

None found. The register holds no published incident that names Weald Farm, Cambridge Road - Solar Farm & Battery Storage. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.