← Back to Essex

Energy sites / United Kingdom / Essex

Battery storage · United Kingdom

Warley Energy Hub, Ockenden - Battery Energy Storage System

Awaiting Construction0.2 MWChecked 6 October 2026Last changed in the dataset 11 September 2025

Technology
Battery storage (Stand-alone Storage)
Capacity
0.2 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
Clearstone Energy Limited
Location
Warley Energy Hub, St Marys Lane North, Ockenden, Upminster, Essex, RM14 3PA, United Kingdom
Planning authority
Havering
Planning application
P1498.24

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 11 November 2024 Planning application submitted
  • 5 August 2025 Planning permission granted
  • 5 August 2030 Planning permission expired

None found. The register holds no published incident that names Warley Energy Hub, Ockenden - Battery Energy Storage System. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 176 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.