← Back to Nottinghamshire

Energy sites / United Kingdom / Nottinghamshire

Battery storage · United Kingdom

Staythorpe Road - Battery energy storage

Under Construction360 MWChecked 6 October 2026Last changed in the dataset 22 September 2025

Technology
Battery storage (Stand-alone Storage)
Capacity
360 MW
Status
Under Construction
Operator or applicant
Ecap Renewables (Elements Green)
Location
S/O Staythorpe Road Staythorpe, Nottinghamshire, NG23, United Kingdom
Planning authority
Newark and Sherwood
Planning application
22/01840/FULM

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 23 November 2022 Planning application submitted
  • 7 July 2023 Planning permission refused
  • 3 May 2024 Planning permission granted
  • 3 May 2024 Appeal granted
  • 1 August 2025 Construction started
  • 3 May 2027 Planning permission expired

None found. The register holds no published incident that names Staythorpe Road - Battery energy storage. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.