Stafford Park - Battery Energy Storage

Awaiting Construction0.2 MWChecked 6 October 2026Last changed in the dataset 16 September 2025

Technology
Battery storage (Stand-alone Storage)
Capacity
0.2 MW
Status
Awaiting Construction (Appeal Granted)
Operator or applicant
AMP Clean Energy
Location
Stafford Park 13, Telford, Shropshire, TF3 3AZ, United Kingdom
Planning authority
Telford and Wrekin
Planning application
TWC/2024/0838

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 13 November 2024 Planning application submitted
  • 8 January 2025 Planning permission refused
  • 2 September 2025 Planning permission granted
  • 2 September 2025 Appeal granted

None found. The register holds no published incident that names Stafford Park - Battery Energy Storage. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents