Planning pack for this site, £295Other options

Battery storage · United Kingdom

Scawby Brook, Brigg - Battery Storage

Operator Centrica Plc · Owner Cbs Energy Storage Assets UK Limited

Awaiting Construction99 MWData checked 16 November 2026Source record dated 26 October 2021

Watch this siteIts outage notices and incidents, what it earns and where it ranks, in your workspace and by email. 7 days free, no card.

Scawby Brook, Brigg - Battery Storage is a 99 MW battery storage site on the edge of Brigg, Lincolnshire, United Kingdom. Its planning application (PA/2021/1288) went to North Lincolnshire on 15 July 2021 and was granted on 9 September 2021. Its status in the Renewable Energy Planning Database (UK government) is awaiting construction. There are 21 other energy sites within 10 km, 3 of them battery storage sites (hybrid battery and solar sites included). The register holds no incident at this site. It holds 14 incidents at battery storage sites (hybrid battery and solar sites included) in the United Kingdom, and 199 worldwide.

9 Oct2 Nov
WholesaleBalancing mechanism

Full revenue and market view The pounds behind each bar, any period back to 2021, where it ranks against every site like it, who trades it, and a side-by-side with any other site.

30 settled days to 7 Nov: 1,449 MWh out and 1,793 MWh in, active 97% of half hours, peak 25 MW of 99. Members see what that output was worth at the market index price, half hour by half hour, and the rate per MW a year.

Contains BMRS data © Elexon Limited copyright and database right (datasets B1610 and MID, the interim settlement run). Read each morning; a settled figure can be revised in later runs.

CENTRICA PLC (03033654), active, since 1995. 3 outstanding charges on the register. Members see the charges register: each charge, when it was created and the lender it is in favour of.

Source: Companies House, matched by the operator's name. If this is the wrong company, tell the editor.

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack for Scawby Brook, Brigg - Battery Storage sets out every comparable incident for this project, with sources. £295, by email in minutes; the order form arrives filled in from this record.

Get the evidence pack for this site, £295 See a sample pack (PDF)

The pack for this site lists 5 comparable battery incidents in the United Kingdom, grid-scale only, nearest first. The nearest is EIR-0584, Fire in a battery container at Rufford Colliery BESS, Rainworth; owner attributes it to a short circuit in NMC cells, 62 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-05842026Fire in a battery container at Rufford Colliery BESS, Rainworth; owner attributes it to a short circuit in NMC cells62 kmSignificant
EIR-06382020Explosion and prolonged fire at Orsted battery storage site in Liverpool160 kmMajor
EIR-00582025Fire in two battery containers at Cirencester Hybrid Solar Farm, Gloucestershire225 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 2 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack
Technology
Battery storage (Stand-alone Storage)
Capacity
99 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
Centrica Plc
Owner
Cbs Energy Storage Assets UK Limited
Location
Power Station Access Roads To Power Station, Scawby Brook Brigg, Lincolnshire, DN20 9LT, United Kingdom
Planning authority
North Lincolnshire
Planning application
PA/2021/1288

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for PA/2021/1288, with what the planning evidence pack adds for this site.

Every application in North Lincolnshire · Alerts for applications and incidents near here

  • 15 July 2021 Planning application submitted
  • 9 September 2021 Planning permission granted

None found. The register holds no published incident that names Scawby Brook, Brigg - Battery Storage. If you know of one, report it (confidential reports are anonymised).

Has Scawby Brook, Brigg - Battery Storage had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names Scawby Brook, Brigg - Battery Storage; it holds 14 incidents at battery storage sites (hybrid battery and solar sites included) in the United Kingdom.
What is the status of Scawby Brook, Brigg - Battery Storage?
Awaiting Construction, in the Renewable Energy Planning Database (UK government), where it last changed on 26 October 2021.
Where is Scawby Brook, Brigg - Battery Storage?
On the edge of Brigg, Lincolnshire, United Kingdom (postcode DN20 9LT).

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).