← Back to Northumberland

Energy sites / United Kingdom / Northumberland

Battery storage · United Kingdom

Quotient Sciences, Taylor Drive - Battery Storage

Awaiting ConstructionChecked 6 October 2026Last changed in the dataset 30 November 2023

Technology
Battery storage (Co-located with RE)
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
The Duke of Northumberland Estate
Location
SW/O Quotient Sciences, S/O Taylor Drive, Alnwick, Northumberland, NE66 2DH, United Kingdom
Planning authority
Northumberland
Planning application
22/03576/RENE

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 19 October 2022 Planning application submitted
  • 9 November 2023 Planning permission granted
  • 9 November 2026 Planning permission expired

None found. The register holds no published incident that names Quotient Sciences, Taylor Drive - Battery Storage. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.