← Back to Kent

Energy sites / United Kingdom / Kent

Battery storage · United Kingdom

Platt Industrial Estate,Maidstone Road - Micro Energy Storage Facility

Revised0.2 MWChecked 6 October 2026Last changed in the dataset 12 November 2024

Technology
Battery storage (Stand-alone Storage)
Capacity
0.2 MW
Status
Revised
Operator or applicant
Aggregated Micro Power Holdings Plc
Location
Maidstone Road, Isles Quarry West, Platt, Borough Green, Sevenoaks, Kent, TN15 8BQ, United Kingdom
Planning authority
Tonbridge and Malling
Planning application
24/00772/PA

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 15 May 2024 Planning application submitted

None found. The register holds no published incident that names Platt Industrial Estate,Maidstone Road - Micro Energy Storage Facility. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.