← Back to Gloucestershire

Energy sites / United Kingdom / Gloucestershire

Battery storage · United Kingdom

Patch Elm Lane - Battery Storage

Awaiting Construction35 MWChecked 6 October 2026Last changed in the dataset 30 March 2022

Technology
Battery storage (Stand-alone Storage)
Capacity
35 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
Green Frog Ventures Limited
Location
Patch Elm Lane Rangeworthy, Gloucestershire, BS37 7LT, United Kingdom
Planning authority
South Gloucestershire
Planning application
P21/07489/F

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 19 November 2021 Planning application submitted
  • 18 March 2022 Planning permission granted
  • 18 March 2025 Planning permission expired

None found. The register holds no published incident that names Patch Elm Lane - Battery Storage. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.