Battery storage · United Kingdom
Parkhouse Road - Battery Energy Storage
Operator GPC 1184 Limited · Owner Gpc 1184 LTD
Awaiting Construction24 MWData checked 16 November 2026Source record dated 19 August 2025
Watch this siteIts outage notices and incidents, what it earns and where it ranks, in your workspace and by email. 7 days free, no card.
Parkhouse Road - Battery Energy Storage is a 24 MW battery storage site on the edge of Barrhead, Glasgow City, United Kingdom. Its planning application (24/00342/FUL) went to Glasgow City on 6 March 2024 and was granted on 8 August 2025. Its status in the Renewable Energy Planning Database (UK government) is awaiting construction. There are 67 other energy sites within 10 km, 21 of them battery storage sites (hybrid battery and solar sites included). The register holds no incident at this site. It holds 14 incidents at battery storage sites (hybrid battery and solar sites included) in the United Kingdom, and 199 worldwide.
Get an email when Parkhouse Road - Battery Energy Storage changes
Free. An email when its status changes: a planning decision, building starting, going live or closing. And each Monday, battery storage incidents in the United Kingdom. No account needed; unsubscribe in one click.
Confirm your email and every battery storage incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack for Parkhouse Road - Battery Energy Storage sets out every comparable incident for this project, with sources. £295, by email in minutes; the order form arrives filled in from this record.
Get the evidence pack for this site, £295 See a sample pack (PDF)
Preview of the planning evidence pack for this site
The pack for this site lists 5 comparable battery incidents in the United Kingdom, grid-scale only, nearest first. The nearest is EIR-0638, Explosion and prolonged fire at Orsted battery storage site in Liverpool, 284 km from this site.
| Reference | Year | Incident | From the site | Severity |
|---|---|---|---|---|
| EIR-0638 | 2020 | Explosion and prolonged fire at Orsted battery storage site in Liverpool | 284 km | Major |
| EIR-0584 | 2026 | Fire in a battery container at Rufford Colliery BESS, Rainworth; owner attributes it to a short circuit in NMC cells | 365 km | Significant |
| EIR-0058 | 2025 | Fire in two battery containers at Cirencester Hybrid Solar Farm, Gloucestershire | 482 km | Significant |
| •••••••• | •••• | •••••••••••••••••••••••••••••• | •••• | •••••• |
| •••••••• | •••• | •••••••••••••••••••••••••••••• | •••• | •••••• |
The first 3 rows as the pack shows them. The other 2 are in the pack, each with its distance, sources and the fire service guidance it bears on.
The map
Summary for this site
This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.
Paragraphs for the planning statement
This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.
In the full packThe site
- Technology
- Battery storage (Stand-alone Storage)
- Capacity
- 24 MW
- Capacity figure from
- Renewable Energy Planning Database (UK government)
- Status
- Awaiting Construction (Planning Permission Granted)
- Operator or applicant
- GPC 1184 Limited
- Owner
- Gpc 1184 LTD
- Location
- S/O 557 Parkhouse Road, Glasgow City, G78 1TE, United Kingdom
- Planning authority
- Glasgow City
- Planning application
- 24/00342/FUL
View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.
The planning application page for 24/00342/FUL, with what the planning evidence pack adds for this site.
Every application in Glasgow City · Alerts for applications and incidents near here
Timeline
- 6 March 2024 Planning application submitted
- 8 August 2025 Planning permission granted
- 8 August 2028 Planning permission runs out
Incidents on the register at this site
None found. The register holds no published incident that names Parkhouse Road - Battery Energy Storage. If you know of one, report it (confidential reports are anonymised).
Questions
- Has Parkhouse Road - Battery Energy Storage had a fire or other incident?
- None is on the register as of 21 November 2026. The register holds no published incident that names Parkhouse Road - Battery Energy Storage; it holds 14 incidents at battery storage sites (hybrid battery and solar sites included) in the United Kingdom.
- What is the status of Parkhouse Road - Battery Energy Storage?
- Awaiting Construction, in the Renewable Energy Planning Database (UK government), where it last changed on 19 August 2025.
- Where is Parkhouse Road - Battery Energy Storage?
- On the edge of Barrhead, Glasgow City, United Kingdom (postcode G78 1TE).
Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).