← Back to West Glamorgan

Energy sites / United Kingdom / West Glamorgan

Battery storage · United Kingdom

Morfa Stadium, Normandy Road - Battery Storage

Awaiting Construction0.2 MWChecked 6 October 2026Last changed in the dataset 9 June 2026

Technology
Battery storage (Stand-alone Storage)
Capacity
0.2 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
AMP Clean Energy
Location
S/O Morfa Stadium, Btw Brunel Way And Normandy Road, West Glamorgan, SA1 5JR, United Kingdom
Planning authority
Swansea
Planning application
2026/0191/FUL

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 5 February 2026 Planning application submitted
  • 24 April 2026 Planning permission granted
  • 24 April 2031 Planning permission expired

None found. The register holds no published incident that names Morfa Stadium, Normandy Road - Battery Storage. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.