← Back to Buckinghamshire

Energy sites / United Kingdom / Buckinghamshire

Solar · United Kingdom

Moat Farm - Solar Farm

Awaiting Construction24.1 MWChecked 6 October 2026Last changed in the dataset 17 March 2022

Technology
Solar
Capacity
24.1 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
Anesco Limited
Location
Moat Farm, Bishopstone, Aylesbury, Buckinghamshire, HP17 8SL, United Kingdom
Planning authority
Buckinghamshire
Planning application
21/03182/APP

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 5 August 2021 Planning application submitted
  • 22 February 2022 Planning permission granted
  • 22 February 2025 Planning permission expired

None found. The register holds no published incident that names Moat Farm - Solar Farm. If you know of one, report it (confidential reports are anonymised).

The register holds 86 incidents at solar farms in the United Kingdom, 59 of them fires, and 344 worldwide. Counts of incidents in published reporting, not rates.

What fails at solar farms · All solar farms incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.