← Back to Wiltshire

Energy sites / United Kingdom / Wiltshire

Battery storage · United Kingdom

Minety Substation

Awaiting Construction10 MWChecked 6 October 2026Last changed in the dataset 12 July 2022

Technology
Battery storage (Co-located with RE)
Capacity
10 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
JBM Solar Project
Location
Land Near Minety Substation, Stonehill, Charlton, Malmesbury, Wiltshire, SN16 9DX, United Kingdom
Planning authority
Wiltshire
Planning application
20/03528/FUL

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 27 April 2020 Planning application submitted
  • 7 April 2022 Planning permission granted
  • 7 April 2025 Planning permission expired

None found. The register holds no published incident that names Minety Substation. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.