Mill Hill National Grid Substation

Awaiting Construction49.9 MWChecked 6 October 2026Last changed in the dataset 27 March 2023

Technology
Battery storage (Stand-alone Storage)
Capacity
49.9 MW
Status
Awaiting Construction (Appeal Granted)
Operator or applicant
Harbour Energy
Location
National Grid Mill Hill Substa, Partingdale Lane, Barnet, London, NW7 1NT, United Kingdom
Planning authority
Barnet
Planning application
20/4241/FUL
Appeal reference
22/00221/AREF

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 16 September 2020 Planning application submitted
  • 7 April 2022 Planning permission refused
  • 8 August 2022 Appeal lodged
  • 13 March 2023 Planning permission granted
  • 13 March 2023 Appeal granted

None found. The register holds no published incident that names Mill Hill National Grid Substation. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.